Bullet train india latest update
India’s first bullet train project — the Mumbai–Ahmedabad High-Speed Rail corridor — is moving ahead rapidly in 2026. The project is being built by NHSRCL with Japanese Shinkansen technology.
Latest major updates
Project progress
Around 55–60% of the overall work is reportedly complete.
The full corridor length is 508 km with 12 stations between Mumbai and Sabarmati/Ahmedabad.
Land acquisition and statutory clearances are now fully completed.
Underground tunnel milestone
A huge breakthrough happened in Mumbai:
India’s largest Tunnel Boring Machines (TBMs) have started work for the underground section.
The line includes India’s first undersea rail tunnel beneath Thane Creek.
Bullet train first look revealed
Today, Indian Railways officially revealed the first visual design of India’s bullet train for the Mumbai–Ahmedabad route.
Expected speed & travel time
The train is expected to:
Run at up to 320 km/h
Reduce Mumbai–Ahmedabad travel time to about 2 hours 7 minutes for limited-stop services.
Indigenous Indian bullet train
India is also developing its own high-speed trainset called the B28.
Prototype rollout target: April 2027
Designed for Indian weather and operating conditions.
Route overview
Major stations planned:
Mumbai (BKC)
Thane
Virar
Boisar
Vapi
Surat
Vadodara
Ahmedabad
Sabarmati and others.
When will it start?
A partial Gujarat section (possibly Surat–Bilimora/Vapi) may open first around 2027.
Full Mumbai–Ahmedabad operations are still expected closer to 2029–2030, though timelines may shift depending on tunneling and station completion.
Official project page
What's the total budget of this?
The Mumbai–Ahmedabad Bullet Train project was originally approved in 2015 at about ₹1.08 lakh crore (around ₹1,08,000 crore).
However, due to:
delays,
inflation,
land acquisition costs,
underground/undersea tunneling,
taxes and utility shifting,
and upgraded indigenous train systems,
the revised estimate in 2026 has risen to around ₹1.98 lakh crore (nearly ₹2 trillion).
Budget comparison
Stage Estimated Cost
Original approval (2015) ~₹1.08 lakh crore Revised estimate (2026) ~₹1.98 lakh crore
That’s roughly an 83% increase over the original estimate.
Who is funding it?
Most of the funding comes from Japan through a very low-interest loan:
About 81% financed by Japan International Cooperation Agency (JICA)
Interest rate is extremely low (around 0.1% for major portions)
Repayment period is about 50 years.
Biggest cost drivers
According to railway committee reports, major increases came from:
Taxes & cess → ~₹29,330 crore
Inflation → ~₹19,084 crore
Land & rehabilitation → ~₹16,695 crore
Indigenous rolling stock & signalling → ~₹16,500 crore.
Want to continue exploring this thread?
Continue this conversation on ChatGPT